Chronology

  • 1 - START HORNING TABLE

    July 2025

  • 2 - SETTING UP WORKSHOP

    July 2025

  • 3 - HORNING TABLE PROGRESS AND ADDED CONTAINER

    August 2025

  • START ASSEMBLING MILL AND COVER HORNING TABLE

    August 2025

  • SET UP MILL

    1 - August 2025

  • FIRST FRAME FUTTOCK TEMPLATE ARRIVES AND IS LAID OUT ON HORNING TABLE

    August 2025

  • FIRST FRAME FUTTOCKS TEMPLATE ON HORNING TABLE

    AUGUST 2025

  • FIRST FRAME FUTTOCKS TEMPLATE ON HORNING TABLE

    August 2025

  • PURPLE HEART FOR BACKBONE ARRIVES

    1 - October 2025

  • PURPLE HEART FOR BACKBONE ARRIVES

    2 - October 2025

  • PURPLE HEART FOR BACKBONE ARRIVES

    3 - October 2025

  • PURPLE HEART FOR BACKBONE ARRIVES

    4 - October 2025

  • PURPLE HEART FOR BACKBONE ARRIVES

    5 - October 2025

  • PURPLE HEART FOR BACKBONE ARRIVES

    6 - October 2025

  • PURPLE HEART FOR BACKBONE ARRIVES

    7 - October 2025

  • FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES

    1 - October 2025

  • FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES

    2 - October 2025

  • FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES

    3 - October 2025

  • FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES

    4 - October 2025

  • FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES

    5 - October 2025

  • SOURCE FOR BLACK LOCUST TRUNNELS SECURED

    October 2025

  • START ASSEMBLY OF BUILDING WAYS

    October 2025

  • ASSEMBLY OF BUILDING WAYS

    October 2025

  • ASSEMBLY OF BUILDING WAYS

    October 2025

  • ASSEMBLY OF BUILDING WAYS

    October 2025

  • ROUGH CUT FIRST FUTTOCKS

    October 2025

  • ROUGH CUT FIRST FUTTOCKS AND CHECK FOR THICKNESS CONFORMITY

    October 2025

  • ROUGH CUT FIRST FUTTOCKS AND CHECK AGAINST TEMPLATE

    October 2025

  • SET UP OF MILLING PROCESS FOR FUTTOCKS

    October 2025

  • SET UP OF MILLING PROCESS FOR FUTTOCKS

    October 2025

  • EXTERNAL BALLAST ARRIVES

    November 2025

  • START SHAPING KEEL PIECES

    November 2025

  • SHAPING KEEL PIECES

    November 2025

  • SHAPING KEEL HOOK SCARPH

    November 2025

  • KEEL HOOK SCARPH WITH RECESSES FOR COAKS AND SHIMS FOR SIKAFLEX SEALER

    November 2025

  • BUILDING WAYS COMPLETE AND READY TO RECIEVE KEEL PIECES

    November 2025

  • START MILLING PIECES OF PURPLE HEART FOR GRIPE ASSEMBLY

    November 2025

  • KEEL LAYING

    December 2025

  • KEEL LAYING

    December 2025

  • KEEL LAYING

    December 2025

  • KEEL LAYING TOAST TO THE PROJECT

    December 2025

  • FIRST FRAME (22) ASSEMBLY ON HORNING TABLE

    December 2025

  • FIRST FRAME (22) ASSEMBLY ON HORNING TABLE

    December 2025

  • FIRST FRAME (22) ASSEMBLY ON HORNING TABLE

    December 2025

  • FIRST FRAME (22) ASSEMBLY ON HORNING TABLE

    December 2025

  • FIRST FRAME (22) ASSEMBLY ON HORNING TABLE

    December 2025

  • FIRST FRAME (22) ASSEMBLY ON HORNING TABLE

    December 2025

  • FIRST FRAME ASSEMBLY ON HORNING TABLE

    December 2025

  • AFT LOWER KEEL PIECE FITTED AND FASTENED

    December 2025

  • FIRST BALLAST PIECE SET UNDER KEEL AND DRILLED FOR BALLAST BOLTS

    December 2025

  • SHAPING INNER STERN POST

    December 2025

  • SET EXTERNAL BALLAST FOR LOCATION OF BALLAST BOLTS THROUGH KEEL

    January 2026

  • SET EXTERNAL BALLAST AND DRILL FOR BALLAST BOLTS THRU KEEL

    January 2026

  • SET EXTERNAL BALLAST AND DRILL FOR BALLAST BOLTS THRU KEEL

    January 2026

  • SHAPING DEADWOOD PIECES

    January 2026

  • SHAPING DEADWOOD PIECES

    January 2026

  • SHAPING DEADWOOD PIECES

    January 2026

  • SHAPING CENTER SECTION OF GRIPE

    1 - January 2026

  • CENTER SECTION OF GRIPE

    2 - January 2026

  • FIRST FRAME (22) ON DUBBING HORSES

    January 2026

  • FIRST FRAME (22) BEVELED AND PAINTED - READY FOR INSTALLATION ON KEEL

    January 2026

  • DEADWOOD A AND B PIECES READY FOR INSTALLATION

    January 2026

  • INNER STERN POST AND DEADWOOD A ON KEEL

    January 2026

  • DEADWOOD A (WITH BALLAST FASTENER KEY-HOLES), KEEL, EXTERNAL BALLAST

    January 2026

  • INNER STERNPOST, LOWER KEEL, KEEL , DEADWOOD, A, B, C

    January 2026

  • FOREFOOT GLUE-UP

    January 2026

  • SETTING FIRST FRAME (22) ON KEEL

    January 2026

  • SETTING FIRST FRAME (22) ON KEEL

    January 2026

  • FIRST FRAME (22) SET ON KEEL WITH TEMPORARY LOCATING CLIP

    January 2026

  • FOREFOOT READY FOR INSTALLATION

    January 2026

  • FRAMES 22 AND 21 ON KEEL

    January 2026

  • GRIPE ASSEMBLY

    February 2026

  • GRIPE ASSEMBLY

    February 2026

  • FRAMES 20, 21, 22 ON KEEL

    February 2026

  • FRAME 23 LIFTING AND WEIGHING

    1 - February 2026

  • FRAME 23 ON DUBBING HORSES - READY FOR FINAL SHAPING AND PAINTING

    2 - February 2026

  • FRAME 23 FINISHING TRUNNELS

    3 - February 2026

  • PREPARED FRAME 23 LIFTING ONTO KEEL

    4 - February 2026

  • FRAMES 19 THROUGH 23 SET ON KEEL

    5 - February 2026

  • 1 AFT ASSEMBLY EPOXY COATED FOR PRESERVATION

    February 2026

  • GRIPE MOUNTED FWD END OF KEEL

    February 2026

  • GRIPE MOUNTED FWD END OF KEEL

    February 2026

  • FRAMES 19 THROUGH 25 MOUNTED MID MONTH

    February 2026

  • STEM BLOCK CENTER PIECES

    February 2026

  • STEM BLOCK CENTER PIECE - WITH TEMPLATE

    February 2026

  • STERN POST AND DEADWOOD A-G

    February 2026

  • FOREFOOT ADDED TO KEEL AND GRIPE

    February 2026

  • START OF STEM PIECE

    March 2026

  • START OF AFT KEELSON LAYOUT, FRAMES 19-26 ON KEEL

    March 2026

  • SETTING AFT KEELSON

    March 2026

  • CONSTRUCTING STEM PIECE

    1 - March 2026

  • CONSTRUCTING STEM PIECE

    2 - March 2026

  • CONSTRUCTING STEM PIECE - LAYING OUT TRUNNEL LOCATIONS

    3 - March 2026

  • CONSTRUCTING STEM PIECE

    4 - March 2026

  • FRAMES 19 THROUGH 27 ON KEEL - MID MONTH

    March 2026

  • KEEL, GRIPE, FOREFOOT AND STERN ASSEMBLY

    1 - March 2026

  • GROWING STEM ASSEMBLY EXPLAINED TO USCG INSPECTOR

    2 - March 2026

  • PLAIN SCARPH FOR AFT KEELSON PREPARED

    March 2026

  • AFT KEELSON FITTED BUT NOT SET WAITING FINAL AFT FULL FRAMES

    March 2026

  • SETTING FRAME 18 TO KEEL - FIRST HEAVY FRAME AT MAINMAST

    March 2026

  • SETTING FRAME 18 TO KEEL

    March 2026

  • FRAMES 17 THROUGH 27 ON KEEL

    March 2026

  • STEM APRON BEING CONSTRUCTED

    1 - March 2026

  • THE OLIVER CUTS OAK FUTTOCKS TO SIZE

    1 - March 2026

  • THE FINE WORK OF THE OLIVER ON SOUTHERN LIVE OAK

    2 - March 2026

  • FRAMES 16 THROUGH 27 ON KEEL

    April 2026

  • FITTING STEM PIECE TO GRIPE AND FOREFOOT

    1 - April 2026

  • STEM PIECE FITTED TO GRIPE AND FOREFOOT

    2 - April 2026

  • SHAPING KEELSON

    April 2026

  • PREPARING STEM APRON

    April 2026

  • FITTING STEM APRON

    April 2026

  • FITTING STEM APRON TO GRIPE AND OUTER STEM PIECE

    April 2026

  • STEM ASSEMBLY LESS STEMSON AND MAIN PIECE

    1 - April 2026

  • USCG INSPECTS PROGRESS OF THE CONSTRUCTION

    2 - April 2026

  • CUTTING REBATES IN DEADWOOD FOR HALF FRAMES

    1 - April 2026

  • CUTTING REBATES IN DEADWOOD FOR HALF FRAMES

    2 - April 2026

  • THE MILLING MASTER EXPLAINS THE PROCESS TO THE COAST GUARD

    April 2026

  • START SHAPING STEMSON

    1 - April 2026

  • START SHAPING STEMSON

    2 - April 2026

  • SHAPING KEELSON

    1 - April 2026

  • FITTING KEELSON SCARPH

    1 - April 2026

  • FRAME 12 READY TO INSTALL - LAST FULL FRAME AFT

    2 - April 2026

  • CREW - BUILDERS

    1 - April 2026

  • CREW - VOLUNTEERS

    2 - April 2026

  • CREW OF BUILDERS AND VOLUNTEERS

    3 - April 2026

  • FRAMES 12 THROUGH 29 ON KEEL

    May 2026

  • STEM ASSEMBLY LESS STEMSON AND MAIN PIECE

    May 2026

  • STEM ASSEMBLY LESS KEELSON PLAIN SCARPH AND HORN TIMBER

    May 2026

  • CUTTING REBATES IN TO DEADWOOD FOR HALF FRAMES

    1 - May 2026

  • ASSEMBLY FRAME 23 (LAST FULL FRAME), REBATE FOR FIRST HALF FRAME

    2 - May 2026

  • FUTTOCKS FRAME 33 IN MILL

    May 2026

  • FITTING KEELSON TO TOPS OF FRAMES

    May 2026

  • FITTING FIRST KEELBOLTS AT FRAME 12 - KEELSON-FRAME-KEEL

    May 2026

  • FITTING FIRST KEELBOLTS AT FRAME 12 - SUKBRNZ ROD WITH WASHERS AND NUTS

    May 2026

  • FIRST KEELBOLTS FITTED AT FRAME 12

    May 2026

  • LOWER STEMSON

    3 - May 2026

  • FRAME 33 PLACED

    4 - May 2026

  • CUTTING REBATES IN DEADWOOD FOR HALF FRAMES STBD SIDE

    1 - May 2026

  • CUTTING REBATES IN DEADWOOD FOR HALF FRAMES STBD SIDE

    2 - May 2026

  • REBATE CUTOUT AND BALLAST BOLT WINDOW PORT SIDE DEADWOOD

    3 - May 2026

  • MARKING STEM ASSEMBLY FOR PLANING RABBETT AND BEARDING LINES

    May 2026

  • FRAMES 12 THROUGH 34 PLACED

    1 - May 2026

  • INTERNAL - FRAMES 34 THROUGH 12 PLACED

    2 - May 2026

  • KEEL BOLTS THROUGH KEELSON-FRAMES-KEEL TO FIRST SCARPH OF KEELSON FRAMES 12 THROUGH 20

    3 - May 2026

  • FRAMES 34 THROUGH 12 PLACED

    4 - May 2026

  • STEM ASSEMBLY LESS STEMSON AND MAIN PIECE

    June 2026

  • LOWER STEMSON ASSEMBLY

    June 2026

  • MARKING STEM FOR HULL PLANKING RABBET AND BEARDING LINE

    June 2026

  • AFT SHIP ASSEMBLY LESS HORN TIMBER

    June 2026

  • FRAME 36 PLACED ON KEEL

    June 2026

  • STERN AND FRAMES 36 THROGH 12 FROM STREET

    1 - June 2026

  • STERN AND FRAMES 12 THROUGH 36 FROM STREET

    2 - June 2026