Chronology
-
1 - START HORNING TABLE
July 2025
-
2 - SETTING UP WORKSHOP
July 2025
-
3 - HORNING TABLE PROGRESS AND ADDED CONTAINER
August 2025
-
START ASSEMBLING MILL AND COVER HORNING TABLE
August 2025
-
SET UP MILL
1 - August 2025
-
FIRST FRAME FUTTOCK TEMPLATE ARRIVES AND IS LAID OUT ON HORNING TABLE
August 2025
-
FIRST FRAME FUTTOCKS TEMPLATE ON HORNING TABLE
AUGUST 2025
-
FIRST FRAME FUTTOCKS TEMPLATE ON HORNING TABLE
August 2025
-
PURPLE HEART FOR BACKBONE ARRIVES
1 - October 2025
-
PURPLE HEART FOR BACKBONE ARRIVES
2 - October 2025
-
PURPLE HEART FOR BACKBONE ARRIVES
3 - October 2025
-
PURPLE HEART FOR BACKBONE ARRIVES
4 - October 2025
-
PURPLE HEART FOR BACKBONE ARRIVES
5 - October 2025
-
PURPLE HEART FOR BACKBONE ARRIVES
6 - October 2025
-
PURPLE HEART FOR BACKBONE ARRIVES
7 - October 2025
-
FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
1 - October 2025
-
FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
2 - October 2025
-
FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
3 - October 2025
-
FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
4 - October 2025
-
FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
5 - October 2025
-
SOURCE FOR BLACK LOCUST TRUNNELS SECURED
October 2025
-
START ASSEMBLY OF BUILDING WAYS
October 2025
-
ASSEMBLY OF BUILDING WAYS
October 2025
-
ASSEMBLY OF BUILDING WAYS
October 2025
-
ASSEMBLY OF BUILDING WAYS
October 2025
-
ROUGH CUT FIRST FUTTOCKS
October 2025
-
ROUGH CUT FIRST FUTTOCKS AND CHECK FOR THICKNESS CONFORMITY
October 2025
-
ROUGH CUT FIRST FUTTOCKS AND CHECK AGAINST TEMPLATE
October 2025
-
SET UP OF MILLING PROCESS FOR FUTTOCKS
October 2025
-
SET UP OF MILLING PROCESS FOR FUTTOCKS
October 2025
-
EXTERNAL BALLAST ARRIVES
November 2025
-
START SHAPING KEEL PIECES
November 2025
-
SHAPING KEEL PIECES
November 2025
-
SHAPING KEEL HOOK SCARPH
November 2025
-
KEEL HOOK SCARPH WITH RECESSES FOR COAKS AND SHIMS FOR SIKAFLEX SEALER
November 2025
-
BUILDING WAYS COMPLETE AND READY TO RECIEVE KEEL PIECES
November 2025
-
START MILLING PIECES OF PURPLE HEART FOR GRIPE ASSEMBLY
November 2025
-
KEEL LAYING
December 2025
-
KEEL LAYING
December 2025
-
KEEL LAYING
December 2025
-
KEEL LAYING TOAST TO THE PROJECT
December 2025
-
FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
FIRST FRAME ASSEMBLY ON HORNING TABLE
December 2025
-
AFT LOWER KEEL PIECE FITTED AND FASTENED
December 2025
-
FIRST BALLAST PIECE SET UNDER KEEL AND DRILLED FOR BALLAST BOLTS
December 2025
-
SHAPING INNER STERN POST
December 2025
-
SET EXTERNAL BALLAST FOR LOCATION OF BALLAST BOLTS THROUGH KEEL
January 2026
-
SET EXTERNAL BALLAST AND DRILL FOR BALLAST BOLTS THRU KEEL
January 2026
-
SET EXTERNAL BALLAST AND DRILL FOR BALLAST BOLTS THRU KEEL
January 2026
-
SHAPING DEADWOOD PIECES
January 2026
-
SHAPING DEADWOOD PIECES
January 2026
-
SHAPING DEADWOOD PIECES
January 2026
-
SHAPING CENTER SECTION OF GRIPE
1 - January 2026
-
CENTER SECTION OF GRIPE
2 - January 2026
-
FIRST FRAME (22) ON DUBBING HORSES
January 2026
-
FIRST FRAME (22) BEVELED AND PAINTED - READY FOR INSTALLATION ON KEEL
January 2026
-
DEADWOOD A AND B PIECES READY FOR INSTALLATION
January 2026
-
INNER STERN POST AND DEADWOOD A ON KEEL
January 2026
-
DEADWOOD A (WITH BALLAST FASTENER KEY-HOLES), KEEL, EXTERNAL BALLAST
January 2026
-
INNER STERNPOST, LOWER KEEL, KEEL , DEADWOOD, A, B, C
January 2026
-
FOREFOOT GLUE-UP
January 2026
-
SETTING FIRST FRAME (22) ON KEEL
January 2026
-
SETTING FIRST FRAME (22) ON KEEL
January 2026
-
FIRST FRAME (22) SET ON KEEL WITH TEMPORARY LOCATING CLIP
January 2026
-
FOREFOOT READY FOR INSTALLATION
January 2026
-
FRAMES 22 AND 21 ON KEEL
January 2026
-
GRIPE ASSEMBLY
February 2026
-
GRIPE ASSEMBLY
February 2026
-
FRAMES 20, 21, 22 ON KEEL
February 2026
-
FRAME 23 LIFTING AND WEIGHING
1 - February 2026
-
FRAME 23 ON DUBBING HORSES - READY FOR FINAL SHAPING AND PAINTING
2 - February 2026
-
FRAME 23 FINISHING TRUNNELS
3 - February 2026
-
PREPARED FRAME 23 LIFTING ONTO KEEL
4 - February 2026
-
FRAMES 19 THROUGH 23 SET ON KEEL
5 - February 2026
-
1 AFT ASSEMBLY EPOXY COATED FOR PRESERVATION
February 2026
-
GRIPE MOUNTED FWD END OF KEEL
February 2026
-
GRIPE MOUNTED FWD END OF KEEL
February 2026
-
FRAMES 19 THROUGH 25 MOUNTED MID MONTH
February 2026
-
STEM BLOCK CENTER PIECES
February 2026
-
STEM BLOCK CENTER PIECE - WITH TEMPLATE
February 2026
-
STERN POST AND DEADWOOD A-G
February 2026
-
FOREFOOT ADDED TO KEEL AND GRIPE
February 2026
-
START OF STEM PIECE
March 2026
-
START OF AFT KEELSON LAYOUT, FRAMES 19-26 ON KEEL
March 2026
-
SETTING AFT KEELSON
March 2026
-
CONSTRUCTING STEM PIECE
1 - March 2026
-
CONSTRUCTING STEM PIECE
2 - March 2026
-
CONSTRUCTING STEM PIECE - LAYING OUT TRUNNEL LOCATIONS
3 - March 2026
-
CONSTRUCTING STEM PIECE
4 - March 2026
-
FRAMES 19 THROUGH 27 ON KEEL - MID MONTH
March 2026
-
KEEL, GRIPE, FOREFOOT AND STERN ASSEMBLY
1 - March 2026
-
GROWING STEM ASSEMBLY EXPLAINED TO USCG INSPECTOR
2 - March 2026
-
PLAIN SCARPH FOR AFT KEELSON PREPARED
March 2026
-
AFT KEELSON FITTED BUT NOT SET WAITING FINAL AFT FULL FRAMES
March 2026
-
SETTING FRAME 18 TO KEEL - FIRST HEAVY FRAME AT MAINMAST
March 2026
-
SETTING FRAME 18 TO KEEL
March 2026
-
FRAMES 17 THROUGH 27 ON KEEL
March 2026
-
STEM APRON BEING CONSTRUCTED
1 - March 2026
-
THE OLIVER CUTS OAK FUTTOCKS TO SIZE
1 - March 2026
-
THE FINE WORK OF THE OLIVER ON SOUTHERN LIVE OAK
2 - March 2026
-
FRAMES 16 THROUGH 27 ON KEEL
April 2026
-
FITTING STEM PIECE TO GRIPE AND FOREFOOT
1 - April 2026
-
STEM PIECE FITTED TO GRIPE AND FOREFOOT
2 - April 2026
-
SHAPING KEELSON
April 2026
-
PREPARING STEM APRON
April 2026
-
FITTING STEM APRON
April 2026
-
FITTING STEM APRON TO GRIPE AND OUTER STEM PIECE
April 2026
-
STEM ASSEMBLY LESS STEMSON AND MAIN PIECE
1 - April 2026
-
USCG INSPECTS PROGRESS OF THE CONSTRUCTION
2 - April 2026
-
CUTTING REBATES IN DEADWOOD FOR HALF FRAMES
1 - April 2026
-
CUTTING REBATES IN DEADWOOD FOR HALF FRAMES
2 - April 2026
-
THE MILLING MASTER EXPLAINS THE PROCESS TO THE COAST GUARD
April 2026
-
START SHAPING STEMSON
1 - April 2026
-
START SHAPING STEMSON
2 - April 2026
-
SHAPING KEELSON
1 - April 2026
-
FITTING KEELSON SCARPH
1 - April 2026
-
FRAME 12 READY TO INSTALL - LAST FULL FRAME AFT
2 - April 2026
-
CREW - BUILDERS
1 - April 2026
-
CREW - VOLUNTEERS
2 - April 2026
-
CREW OF BUILDERS AND VOLUNTEERS
3 - April 2026
-
FRAMES 12 THROUGH 29 ON KEEL
May 2026
-
STEM ASSEMBLY LESS STEMSON AND MAIN PIECE
May 2026
-
STEM ASSEMBLY LESS KEELSON PLAIN SCARPH AND HORN TIMBER
May 2026
-
CUTTING REBATES IN TO DEADWOOD FOR HALF FRAMES
1 - May 2026
-
ASSEMBLY FRAME 23 (LAST FULL FRAME), REBATE FOR FIRST HALF FRAME
2 - May 2026
-
FUTTOCKS FRAME 33 IN MILL
May 2026
-
FITTING KEELSON TO TOPS OF FRAMES
May 2026
-
FITTING FIRST KEELBOLTS AT FRAME 12 - KEELSON-FRAME-KEEL
May 2026
-
FITTING FIRST KEELBOLTS AT FRAME 12 - SUKBRNZ ROD WITH WASHERS AND NUTS
May 2026
-
FIRST KEELBOLTS FITTED AT FRAME 12
May 2026
-
LOWER STEMSON
3 - May 2026
-
FRAME 33 PLACED
4 - May 2026
-
CUTTING REBATES IN DEADWOOD FOR HALF FRAMES STBD SIDE
1 - May 2026
-
CUTTING REBATES IN DEADWOOD FOR HALF FRAMES STBD SIDE
2 - May 2026
-
REBATE CUTOUT AND BALLAST BOLT WINDOW PORT SIDE DEADWOOD
3 - May 2026
-
MARKING STEM ASSEMBLY FOR PLANING RABBETT AND BEARDING LINES
May 2026
-
FRAMES 12 THROUGH 34 PLACED
1 - May 2026
-
INTERNAL - FRAMES 34 THROUGH 12 PLACED
2 - May 2026
-
KEEL BOLTS THROUGH KEELSON-FRAMES-KEEL TO FIRST SCARPH OF KEELSON FRAMES 12 THROUGH 20
3 - May 2026
-
FRAMES 34 THROUGH 12 PLACED
4 - May 2026
-
STEM ASSEMBLY LESS STEMSON AND MAIN PIECE
June 2026
-
LOWER STEMSON ASSEMBLY
June 2026
-
MARKING STEM FOR HULL PLANKING RABBET AND BEARDING LINE
June 2026
-
AFT SHIP ASSEMBLY LESS HORN TIMBER
June 2026
-
FRAME 36 PLACED ON KEEL
June 2026
-
STERN AND FRAMES 36 THROGH 12 FROM STREET
1 - June 2026
-
STERN AND FRAMES 12 THROUGH 36 FROM STREET
2 - June 2026