Chronology
-
1 - START HORNING TABLE
July 2025
-
2 - SETTING UP WORKSHOP
July 2025
-
3 - HORNING TABLE PROGRESS AND ADDED CONTAINER
August 2025
-
4 - START ASSEMBLING MILL AND COVER HORNING TABLE
August 2025
-
5 - SET UP MILL
August 2025
-
6 - FIRST FRAME FUTTOCK TEMPLATE ARRIVES AND IS LAID OUT ON HORNING TABLE
August 2025
-
7 - FIRST FRAME FUTTOCKS TEMPLATE ON HORNING TABLE
August 2025
-
8 - FIRST FRAME FUTTOCKS TEMPLATE ON HORNING TABLE
August 2025
-
9 - PURPLE HEART FOR BACKBONE ARRIVES
October 2025
-
10 - PURPLE HEART FOR BACKBONE ARRIVES
October 2025
-
11 - PURPLE HEART FOR BACKBONE ARRIVES
October 2025
-
12 - PURPLE HEART FOR BACKBONE ARRIVES
October 2025
-
13 - PURPLE HEART FOR BACKBONE ARRIVES
October 2025
-
14 - PURPLE HEART FOR BACKBONE ARRIVES
October 2025
-
15 - PURPLE HEART FOR BACKBONE ARRIVES
October 2025
-
16 - FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
October 2025
-
17 - FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
October 2025
-
18 - FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
October 2025
-
19 - FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
October 2025
-
20 - FIRST LOAD OF SOUTHERN LIVE OAK FOR HULL FRAMING ARRIVES
October 2025
-
21- SOURCE FOR BLACK LOCUST TRUNNELS SECURED
October 2025
-
22 - START ASSEMBLY OF BUILDING WAYS
October 2025
-
23 - ASSEMBLY OF BUILDING WAYS
October 2025
-
24 - ASSEMBLY OF BUILDING WAYS
October 2025
-
25 - ASSEMBLY OF BUILDING WAYS
October 2025
-
26 - ROUGH CUT FIRST FUTTOCKS
October 2025
-
27 - ROUGH CUT FIRST FUTTOCKS AND CHECK FOR THICKNESS CONFORMITY
October 2025
-
28 - ROUGH CUT FIRST FUTTOCKS AND CHECK AGAINST TEMPLATE
October 2025
-
29 - SET UP OF MILLING PROCESS FOR FUTTOCKS
October 2025
-
30 - SET UP OF MILLING PROCESS FOR FUTTOCKS
October 2025
-
31 - EXTERNAL BALLAST ARRIVES
November 2025
-
32 - START SHAPING KEEL PIECES
November 2025
-
33 - SHAPING KEEL PIECES
November 2025
-
34 - SHAPING KEEL HOOK SCARPH
November 2025
-
35 - KEEL HOOK SCARPH WITH RECESSES FOR COAKS AND SHIMS FOR SIKAFLEX SEALER
November 2025
-
36 - BUILDING WAYS COMPLETE AND READY TO RECIEVE KEEL PIECES
November 2025
-
37 - START MILLING PIECES OF PURPLE HEART FOR GRIPE ASSEMBLY
November 2025
-
38 - KEEL LAYING
December 2025
-
39 - KEEL LAYING
December 2025
-
40 - KEEL LAYING
December 2025
-
41 - KEEL LAYING TOAST TO THE PROJECT
December 2025
-
42 - FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
43 - FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
44 - FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
45 - FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
46 - FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
47 - FIRST FRAME (22) ASSEMBLY ON HORNING TABLE
December 2025
-
48 - FIRST FRAME ASSEMBLY ON HORNING TABLE
December 2025
-
49 - AFT LOWER KEEL PIECE FITTED AND FASTENED
December 2025
-
50 - FIRST BALLAST PIECE SET UNDER KEEL AND DRILLED FOR BALLAST BOLTS
December 2025
-
51 - SHAPING INNER STERN POST
December 2025
-
52 - SET EXTERNAL BALLAST FOR LOCATION OF BALLAST BOLTS THROUGH KEEL
January 2026
-
53 - SET EXTERNAL BALLAST AND DRILL FOR BALLAST BOLTS THRU KEEL
January 2026
-
54 - SET EXTERNAL BALLAST AND DRILL FOR BALLAST BOLTS THRU KEEL
January 2026
-
55 - SHAPING DEADWOOD PIECES
January 2026
-
56 - SHAPING DEADWOOD PIECES
January 2026
-
57 - SHAPING DEADWOOD PIECES
January 2026
-
58 - SHAPING CENTER SECTION OF GRIPE
January 2026
-
59 - CENTER SECTION OF GRIPE
January 2026
-
60 - FIRST FRAME (22) ON DUBBING HORSES
January 2026
-
61 - FIRST FRAME (22) BEVELED AND PAINTED - READY FOR INSTALLATION ON KEEL
January 2026
-
62 - DEADWOOD A AND B PIECES READY FOR INSTALLATION
January 2026
-
63 - INNER STERN POST AND DEADWOOD A ON KEEL
January 2026
-
64 - DEADWOOD A (WITH BALLAST FASTENER KEY-HOLES), KEEL, EXTERNAL BALLAST
January 2026
-
65 - INNER STERN POST, LOWER KEEL, KEEL, DEADWOOD A, B, C
January 2026
-
66 - FOREFOOT GLUE-UP
January 2026
-
67 - SETTING FIRST FRAME (22) ON KEEL
January 2026
-
68 - SETTING FIRST FRAME (22) ON KEEL
January 2026
-
69 - FIRST FRAME (22) SET ON KEEL WITH TEMPORARY LOCATING CLIP
January 2026
-
70 - FOREFOOT READY FOR INSTALLATION
January 2026
-
71 - FRAMES 22 AND 21 ON KEEL
January 2026
-
72 - GRIPE ASSEMBLY
February 2026
-
73 - GRIPE ASSEMBLY
February 2026
-
74 - FRAMES 20, 21, 22 ON KEEL
February 2026
-
75 - FRAME 23 LIFTING AND WEIGHING
February 2026
-
76 - FRAME 23 ON DUBBING HORSES READY FOR FINAL SHAPING AND PAINTING
February 2026
-
77 - FRAME 23 FINISHING TRUNNELS
February 2026
-
78 - PREPARED FRAME 23 LIFTING ONTO KEEL
February 2026
-
79 - FRAMES 19 THRU 23 SET ON KEEL
February 2026
-
80 - 1 AFT ASSEMBLY EPOXY COATED FOR PRESERVATION
February 2026
-
81 - GRIPE MOUNTED FWD END OF KEEL
February 2026
-
82 - GRIPE MOUNTED FWD END OF KEEL
February 2026
-
83 - FRAMES 19 THROUGH 25 MOUNTED MID MONTH
February 2026
-
84 - STEM BLOCK CENTER PIECES
February 2026
-
85 - STEM BLOCK CENTER PIECE - WITH TEMPLATE
February 2026
-
86 - STERN POST AND DEADWOOD A-G
February 2026
-
87 - FOREFOOT ADDED TO KEEL AND GRIPE
February 2026
-
88 - START OF STEM PIECE
March 2026
-
89 - START AFT KEELSON LAYOUT, FRAMES 19-26 ON KEEL
March 2026
-
90 - SETTING AFT KEELSON
March 2026
-
91 - CONSTRUCTING STEM PIECE
March 2026
-
92 - CONSTRUCTING STEM PIECE
March 2026
-
93 - CONSTRUCTING STEM PIECE - LAYING OUT TRUNNEL LOCATIONS
March 2026
-
94 - CONSTRUCTING STEM PIECE
March 2026
-
95 - FRAMES 19 THRU 27 ON KEEL - MID MONTH
March 2026
-
96 - KEEL, GRIPE, FOREFOOT, AND STEM ASSEMBLY
March 2026
-
97 - GROWING STEM ASSEMBLY EXPLAINED TO USGC
March 2026
-
98 - PLAIN SCARPH FOR AFT KEELSON
March 2026
-
99 - AFT KEELSON FITTED BUT NOT SET WAITING FINAL AFT FULL FRAMES
March 2026
-
100 - SETTING FRAME 18 TO KEEL - FIRST HEAVY FRAME AT MAINMAST
March 2026
-
101 - SETTING FRAME 18 TO KEEL
March 2026
-
102 - FRAMES 17 THRU 27 ON KEEL
March 2026
-
103 - STEM APRON BEING CONSTRUCTED
March 2026
-
104 - THE OLIVER CUTS OAK FUTTOCKS TO SIZE
March 2026
-
105 - THE FINE WORK OF THE OLIVER ON SOUTHERN LIVE OAK
March 2026
-
106 - FRAMES 16 THRU 27 ON KEEL
April 2026
-
107 - FITTING STEM PIECE TO GRIPE AND FOREFOOT
April 2026
-
108 - STEM PIECE FITTED TO GRIPE AND FOREFOOT
April 2026
-
109 - SHAPING KEELSON
April 2026
-
110 - PREPARING STEM APRON
April 2026
-
111 - FITTING STEM APRON
April 2026
-
112 - FITTING STEM APRON TO GRIPE AND OUTER STEM PIECE
April 2026
-
113 - STEM ASSEMBLY LESS STEMSON AND MAIN PIECE
April 2026
-
114 - USCG INSPECTS PROGRESS OF THE CONSTRUCTION
April 2026
-
115 - CUTTING REBATES IN DEADWOOD FOR HALF FRAMES
April 2026
-
116 - CUTTING REBATES IN DEADWOOD FOR HALF FRAMES
April 2026
-
117 - THE MILLING MASTER EXPLAINS THE PROCESS TO THE COAST GUARD
April 2026
-
118 - START SHAPING STEMSON
April 2026
-
119 - START SHAPING STEMSON
April 2026
-
120 - SHAPING KEELSON
April 2026
-
121 - FITTING KEELSON SCARPH
April 2026
-
122 - FRAME 12 READY TO INSTALL - LAST FULL FRAME AFT
April 2026
-
123 - CREW - BUILDERS
April 2026
-
124 - CREW - VOLUNTEERS
April 2026
-
125 - CREW OF BUILDERS AND VOLUNTEERS
April 2026
-
126 - FRAMES 12 THRU 29
May 2026
-
127 - STEM ASSEMBLY IN PLACE LESS STEMSON AND MAIN PIECE
May 2026
-
128 - STERN ASSEMBLY IN PLACE LESS PLAIN SCARPH AND HORN TIMBER
May 2026
-
129 - UPPER STEMSON PIECE
May 2026
-
130 - LOWER STEMSON PIECE
May 2026
-
131 - CUTTING REBATES INTO DEADWOOD FOR HALF FRAMES
May 2026
-
132 - ASSEMBLY FRAME 12 (LAST FULL FRAME), REBATE FOR FIRST HALF FRAME
May 2026
-
133 - FUTTOCKS FRAME 33 IN MILL
May 2026
-
134 - FITTING KEELSON TO TOPS OF FRAMES
May 2026
-
135 - FITTING FIRST KEEL BOLTS AT FRAME 12 - KEELSON - FRAME - KEEL
May 2026
-
136 - FITTING KEEL BOLTS FRAME 12 - SILBRNZ ROD WITH WASHERS AND NUTS
May 2026
-
137 - FIRST KEEL BOLTS FITTED AT FRAME 12
May 2026
-
138 - LOWER STEMSON
May 2026
-
139 - FRAME 33 PLACED
May 2026
-
140 - CUTTING REBATES IN DEADWOOD FOR HALF FRAMES STBD SIDE
May 2026
-
141 - CUTTING REBATES IN DEADWOOD FOR HALF FRAMES FOR STBD SIDE
May 2026
-
142 - REBATE CUTOUT AND BALLAST BOLT WINDOW PORT SIDE DEADWOOD
May 2026
-
143 - MARKING STEM ASSEMBLY FOR PLANKING RABBIT AND BEARDING LINES
May 2026
-
144 - FRAMES 12 THRU 34 PLACED
May 2026
-
145 - INTERNAL - FRAMES 34 - 12 PLACED
May 2026
-
146 - KEEL BOLTS THROUGH KEELSON - FRAMES - KEEL - TO FIRST SCARPH OF KEELSON FRAMES 12 THRU 20
May 2026
-
147 - FRAMES 34 THRU 12 PLACED
May 2026
-
148 - STEM ASSEMBLY LESS STEMSON AND MAIN PIECE
June 2026
-
149 - LOWER STEMSON ASSEMBLY
June 2026
-
150 - MARKING STEM FOR HULL PLANKING RABBET AND BEARDING LINE
June 2026
-
151 - AFT SHIP ASSEMBLY LESS HORN TIMBER
June 2026
-
152 - FRAME 36 PLACED ON KEEL
June 2026
-
153 - STEM AND FRAMES 36 THRU 12 FROM STREET
June 2026
-
154 - STERN AND FRAMES 12 THRU 36 FROM STREET
June 2026